Release Notes - 23rd September 2025

Bug Fixes

  • Cost/Volume Profile Graphs: Resolved an issue where the info banner that displays when more than 30 results are returned was incorrectly returning the count of results when certain option filters were applied.

Release Notes - 17th September 2025

General Updates

  • WT5x: When hovering over the help text for an asset, we now display the help description for the asset group e.g. Tail cables included
  • Generic Non-Area Interventions: Now renamed to Generic (Non Asset) Interventions

Bug Fixes

  • Interventions: Resolved an error where Level Crossing child projects could not be created if missing a route ID.
  • Interventions: Resolved an error which would occur when creating a new intervention for a level crossing, adding a Work type and a date then removing the Work type and date.
  • CP Planning Views: Resolve an error which would prevent exporting to CSV from the Package or Asset views.
  • WT5x: Resolve an issue where unit rates were being stored to 2 decimal places instead of 4.

Release Notes - 16th September 2025

This release contains some tweaks to Cost and Volume Outputs and some modifications to the search function within the Workbank:

  1. New Package CapEx Costs has been renamed CP Planning Package View.
  2. Asset CapEx Costs has been renamed CP Planning Asset View.
  3. Both outputs now include:
    • The selected and the next Control Period's data.
    • A breakdown of costs by year for the selected and next control period.
    • The Whole values for SEU CAV, SEU DAV and AFC for the Package/Intervention, regardless of the Control Period those values are triggered.
  4. The search box on the Workbank pages (Calendars, Table outputs, etc.) now requires pressing 'Enter' to search. Previously typing in this field would automatically update the page, which could lead to unwanted page updates if the search term was incorrectly formed.

Release Notes - 15th September 2025

A major update to Rail BI was released. This included many new features and changes to existing features.

You can see highlights below, please click on the links to learn more about any of the new features available.

Generic Non-Area Interventions

Generic (Non-Area) Interventions are interventions that do not yet have an assigned asset area. These can be created where work is set to be completed on a route, but no assigned asset area is set for the work.

Project Delivered Activity Volume (DAV) Override

The KVL on an intervention can now be overridden and in turn, this now updates the DAV whilst keeping the asset work type unchanged.

Change Requests

We've continued to add improvements to our recently released Change Requests feature, which allows users of all permission levels to suggest changes to the workbank or to delivery, for the routes default approver to approve or reject.

Introducing 'Auth Service'

A new central application for administrators to manage user accounts across the full suite of Rail BI applications

Bug Fixes

  • Categories: Resolved an issue where categories could not be assigned to Work Types in the work type configuration.

Release Notes - 10th September 2025

This update contains bug fixes.

Bug Fixes

  • Workbank Duplication: Resolved an issue preventing options being duplicated when a route filter was applied.
  • Workbank Filters: Resolved an issue where using the 'OR' operator would display an error.

Release Notes - 9th September 2025

This update contains bug fixes.

Bug Fixes

  • Workbank Export: Resolved an issue where the export "CSV For Import inc Automated Renewals" would fail from published options that contained assets since removed during SSADS import.

Release Notes - 12th August 2025

This update contains bug fixes.

Bug Fixes

  • Workbank Export: Resolved an issue where the export "CSV For Import" would fail
  • Workbank View: Resolved an issue where year filters would not persist on page refresh

Release Notes - 30th July 2025

This update contains bug fixes.

Bug Fixes

  • Options: Fixed an error from preventing options from caching if the option duration was too short to span an entire control period
  • Workbank View: Resolved an issue whereby Post-Comm SEU Count was incorrect after export.

Release Notes - 29th July 2025

This update contains general updates and bug fixes.

Bug Fixes

  • Option Filters: Resolved an issue whereby filtering by Work Type = Minor Works displayed no results.

General Updates

  • CP Planning Asset View: SSADS LX Only toggle has been added for Signalling & LX costs.
  • CP Planning Asset View: Costs are now broken down by year for future Control Period.
  • Cost Profile: Export option is now available on the cost profile breakdown.
  • Delivery Reporting: Selecting a column in the costs graph now displays a cost breakdown.
  • CP Planning Package View: Costs are now broken down by year for future Control Period.

Release Notes - 22nd July 2025

This update contains bug fixes.

Bug Fixes

  • Option Logs: Resolved an error where AFC is showing as updated when unedited.
  • Option Logs: Resolved an error whereby dates are formatted incorrectly.
  • Workbank Calendar: Resolved an error whereby responsive calendar layout could stop menus from opening.

Release Notes - 20th July 2025.

On 20/07/2025, a major update to Rail BI was released. This included many new features and changes to existing features.

You can see highlights below, please click on the links to learn more about any of the new features available. Alternatively, our full documentation is available here.

Terminology Change

Projects have now been renamed to Interventions. This more closely reflects industry standard terminology.

Option Logs

We've added a new entry to the left hand side bar. Here you can access the new Change Requests feature and Audit Logs (which were previously available in Option Settings).

Change Requests allow data changes to be proposed and updated with a full approval process and audit history.

  • Affected Area (including Post-Intervention SEUs)
  • Commissioning Dates
  • Work Types
  • BP Costs & Volumes

Default Approvers can be set on a per-route basis.

Programme Date maps

A new Programme Date map is available in the Maps module by selecting Programme Dates from the Map Type.

This allows the user to step through different control periods (or years) and displays the interventions within each different time period.

General Updates

  • If an intervention has an SCO or OP number, a banner will recommend data changes are made via Change Proposal in the Change Request section.

  • Option Adjustments: A change reason is now required when completing an option adjustment. This is displayed in the Option Audit Log.

The following tab names have been changed in the Package Delivery Modal:

  • Change log has been renamed to Audit Log.
  • Estimates (BP) has been renamed to BP Costs & Volumes.
  • Actuals (OP) has been renamed to OP Costs & Volumes.
  • Add Estimates has been renamed Add Change Proposal.

Release Notes - 17th July 2025

This release contains bug fixes.

Bug Fixes

  • Workbank Options: Resolved an issue where export options would be missing.
  • Deferred Renewals: Resolved an issue where the dashboard would not load.

Release Notes - 15th July 2025

This release contains bug fixes.

Bug Fixes

  • Workbank Options: Resolved an issue whereby exports would hang while an option is being rebuild.
  • Workbank Options: Resolved an issue whereby the throbber would not be displayed when updating data.